Shuyler Creek Trail Expansion

Project Facts:

  • 10’ Wide Asphalt Trail

  • Grade separated pedestrian crossing at Farm Road 99

  • Trail along south side of Farm Road 182 to Wilson's Creek National Battlefield

  • Estimated total construction cost: $1.7-$2.2 million

  • Funded by MoDOT Surface Transportation Block Grant

  •  20% Local Match – Republic Capital Investment Sales Tax Fund

Republic's trails, and expansion of the trail system, are frequently mentioned and prioritized by citizens, as evidenced by the 2021 Citizen Survey. Read more here.
Read the Transportation Analysis Here.


Interactive Trail Map

Typical Cross-Section

Document


Trail Connectivity:

  • Existing Trails

    • Shuyler Creek Trail
    • Wilson’s Creek National
    • Battlefield Loop
    • Wilson’s Creek Greenway
  • Funded Future Trails

    • Shuyler Creek Extension
    • Wilson’s Creek Boulevard Trail
    • MoDOT Wilson’s Creek Battlefield Connector
  • Planned Alignments/Trails

    • West Republic Trail
    • Wilson’s Creek Greenway

Project Timeline:

  • August 2021 to January 2022 – Environmental Review
  • November 2021 – Public Meeting
  • Winter/Spring 2022 – Right-of-Way Acquisition
  • Fall 2022 – Project Award
  • Winter/Spring 2023 – Construction

Property owners, click here for more information.


Ozark Transportation Organization Trail Investment StudyOTO_Trail_Investment_Study_pgs 52-53-1

OTO_Trail_Investment_Study_pgs 52-53-2

Read the full OTO Trail Investment Survey here.