Project Facts:
10’ Wide Asphalt Trail
Grade separated pedestrian crossing at Farm Road 99
Trail along south side of Farm Road 182 to Wilson's Creek National Battlefield
Estimated total construction cost: $1.7-$2.2 million
Funded by MoDOT Surface Transportation Block Grant
20% Local Match – Republic Capital Investment Sales Tax Fund
Republic's trails, and expansion of the trail system, are frequently mentioned and prioritized by citizens, as evidenced by the 2021 Citizen Survey. Read more here.
Read the Transportation Analysis Here.
Interactive Trail Map
Typical Cross-Section

Trail Connectivity:
Existing Trails
- Shuyler Creek Trail
- Wilson’s Creek National
- Battlefield Loop
- Wilson’s Creek Greenway
Funded Future Trails
- Shuyler Creek Extension
- Wilson’s Creek Boulevard Trail
- MoDOT Wilson’s Creek Battlefield Connector
Planned Alignments/Trails
- West Republic Trail
- Wilson’s Creek Greenway
Project Timeline:
- August 2021 to January 2022 – Environmental Review
- November 2021 – Public Meeting
- Winter/Spring 2022 – Right-of-Way Acquisition
- Fall 2022 – Project Award
- Winter/Spring 2023 – Construction